Retaining Wall Installation

For most non-critical walls, and under favorable soil conditions, Nicolock wall units are constructed as a conventional gravity wall system. Walls up to 3 feet in height (2 ft. 6 in. for Sierra) are attainable without the need for soil reinforcement (Geogrid). Recommended installation procedures should be followed to ensure the life of your wall structure.

TOP_install_wall
  1. Wall Cap
  2. 3/4” Crushed Clean Stone
  3. Top Soil
  4. Existing Site Soil
  5. Reinforced Soil
  6. Filter Fabric (as required)
  7. Geogrid (as required)
  8. 3/4” Processed aggregate Footing
  9. Drainage Pipe (as required)
  10. Foundation Soil


IMPORTANT!
Illustration shown is not for construction purpose. Please confer with your local engineer for proper placement of geogrid.

IMPORTANT! Walls higher than 36" above grade, terraced walls, weak soils and other loading conditions require special considerations in design and construction. This should be done by a qualified engineer & a professional contractor. Check with you local building department for code requirements.

The following Installing procedures apply to all Nicolock Retaining Wall Units constructed as a conventional Gravity Wall system.

PREPARING / EXCAVATING. Before beginning excavation, make sure there are no utility lines in the wall area. Excavate area to the proper depth. For geogrid-reinforced retaining walls or for more detailed information, consult your local distributor or contact Nicolock.

01_install_wall


TRENCH EXCAVATION

Excavate a trench a minimum of 6" beyond the front and back of the wall block. Dig trench 9” to 14” deep, enough to create a 6” thick leveling pad and to bury at least one whole wall block below grade. Compact the soil at the bottom of trench. Shape the slope behind wall to allow for 12” of drainage material.

02_install_wall


TRENCH FILL

Place filter fabric in trench and up the cut slope. Fill trench with clean, graded aggregate and compact.

03_install_wall


BASE BLOCKS

Position a level string line at the straight face of the unit to maintain alignment. Place the wall units side by side in the center of the prepared base. Bury the first course of block to a depth equal to 10% of the height of the wall, measured in inches. Level units from side to side, front to back.

04_install_wall


DRAINAGE SET-UP

Fill the space in front of wall with clean fill to grade to hold units from shifting. Place a perforated pipe behind wall on top of base for drainage. Fill drainage area with clean aggregate keeping filter fabric in place. Backfill soil on outer side of fabric and compact.

05_install_wall


STACKING UNITS

Place successive courses by fitting the keys and grooves onto the units in the row below (if applicable).  Keep the tops of each course clean to maintain a level surface. Stack units in a running bond pattern (crossing joints).

06_install_wall


BACKFILL & FINISHING

Continue building the wall to the desired height. Backfill with clean aggregate behind each course as completed. Backfill and compact soil. Finish the wall by securing the wall cap with a suitable masonry adhesive.

  • NICE 2015
  • Outdoor Living
  • Stormwater Solutions
  • Lookbook
  • Rosetta by Nicolock
  • Looks Like Natural Stone

NICE workshops for Contractors will kick-off in January 2015. Registration details coming soon!

Read More...

Rosetta By Nicolock

Extend the use of your Nicolock patio with the addition of a handsome Outdoor Living feature or two!

Read More...

Prevents flooding

Prevent flooding and reduce runoff with Nicolock environmental pavers!

Read More...

Rosetta By Nicolock

Rosetta Hardscapes accurately creates the look and feel of nature in any application you imagine.

Read More...

Looks Like Natural Stone

Bradstone Looks Like Natural Stone

They wanted a natural look in quality, texture, and color. Bradstone by Nicolock was the answer.

View now...